In typical commercial installations across Pakistan, "commissioning" consists of turning on the monitor, confirming that pictures appear on screen, and collecting the check. Months later, when an incident occurs, the security team discovers that the license plate camera is out of focus, the entrance camera is blinded by sunlight glare, and recordings were quietly overwritten two weeks ago.
A professional CCTV commissioning process is a rigorous engineering gate. Here are the mandatory checkpoints your installer must document before handover:
1. Optical Alignment to DORI Standards (EN 62676-4)
Security cameras are not decorative. Under international standards (EN 62676-4), every camera field of view is categorized by pixel density on target:
- Detection (25 px/meter): Capable of seeing whether a human or vehicle is present.
- Observation (62 px/meter): Capable of viewing characteristic details like clothing color.
- Recognition (125 px/meter): High enough clarity to recognize a known person with high confidence.
- Identification (250 px/meter): Pinpoint facial resolution sufficient for legal court evidence.
Your commissioning checklist must state the exact DORI target classification for every camera on the floor plan.
2. Bit-Rate and Retention Storage Verification
Never assume an NVR with 8 TB will record 16 cameras for 30 days. Hard drive capacity must be verified against actual measured bitrates during daytime peak motion and nighttime noise conditions.
Under State Bank of Pakistan (SBP) circular requirements for bank branches, footage must be retained for at least 30 days continuous recording without frame skipping. The commissioning report must record the exact NVR storage calculation and RAID array status (RAID 5/6 recommended for disk failure tolerance).
3. Network Cybersecurity & Hardening
Unsecured IP cameras are notorious entry points for enterprise network malware and DDoS botnets. Before final sign-off, verify:
- Default passwords (`admin/admin`, `123456`) are permanently disabled.
- Camera firmware is updated to the latest manufacturer patch level.
- All camera streams are confined to a dedicated Security VLAN with no direct routing to the corporate Internet except via an authenticated VMS gateway.
- Unused network ports (Telnet, UPnP, HTTP) are disabled in favor of HTTPS/TLS.
4. The Commissioning Sign-Off Checklist Format
| Test Item | Standard Criteria | Verification Method |
|---|---|---|
| Angle & Focus | DORI pixels/meter verified | Visual test target captured at entrance boundary |
| Night IR Transition | IR cut filter switches cleanly < 2 lux | Simulated ambient blackout test |
| WDR Balance | Facial detail clear against backlit glass doors | High-contrast backlight Lux meter audit |
| Storage Retention | Meets mandated SBP / corporate days | NVR FIFO recording calculation audit |
| Fail-Safe Trip | Door locks release upon fire alarm trigger | Physical fire loop alarm test activation |
Need an Audit of Your Installed Camera System?
SolidCore's engineers conduct complete optical and storage health audits across Karachi, Lahore, and Islamabad.